Requested delivery: 2026-11-30 ยท Backend Engineering
Push the Regional Rollout start from 13 Oct to 3 Nov, absorbing the shortfall without adding headcount.
Bring in 2 contract backend engineers for 8 weeks to close the gap and hold the current date.
Reassign 1.5 FTE currently shared with Nova Customer Platform back to Atlas for 6 weeks.
Defer the Vietnam statutory report pack to Regional Rollout, launching Thailand and Singapore reporting first.
Backend engineering capacity for the 6 weeks before UAT is 3.2 FTE against 5.1 FTE required.
Nova Customer Platform's shared backend allocation is the largest single claim on the same engineers Atlas needs.
Holding the current 30 Nov delivery date without a capacity change would very likely cost another 2-3 weeks of undocumented slip, the way Vietnam statutory reporting already has.
Move Project Nova's shared backend allocation back to Atlas for 6 weeks. It recovers 8 days without new spend, and Nova's own timeline has more slack to absorb the loan than Atlas has to absorb the shortfall.
Reassign 1.5 FTE from Nova Customer Platform to Atlas Regional Finance Transformation, effective next sprint, for 6 weeks, pending your approval.