62/100 · rule set SQ-2026.1 · 6 findings
Affects: Vietnam statutory report pack, UAT, UAT sign-off
Affects: UAT
Affects: UAT sign-off
Affects: Bank & Tax Integrations
Affects: Regional Reporting Engine
Affects: Vietnam statutory report pack, UAT
The critical path into UAT sign-off currently carries 12 days of negative float.
Schedule integrity has declined from 78 to 62 over the last 3 weeks, driven by the Vietnam statutory report pack slipping twice.
A milestone's business owner may not be the same person as the phase lead once a project reaches Governed profile. See 10-PERMISSIONS-AND-GOVERNANCE.md.
At the current burn rate, UAT sign-off is more likely to land in the week of 26 Oct than on the current 12 Oct target date.
Convert UAT's start constraint to "as soon as possible" and re-baseline once the capacity decision below is made, so the constraint stops hiding the real date.